The Port of Seattle promised the contractors equitable compensation for added and changed work if this marine, conference and restaurant complex was completed on time. When the resolution process stalled near the end of the project, Amento Group was jointly hired by the Port, general and prime subcontractors, and partnering consultant as the project neutral.
Our team initiated a cooperative claims resolution process and facilitated the settlement of multiple cost and schedule disputes. All issues were resolved with routine change orders and without legal intervention.